Training
Operators were training on 6/22 and got hands-on training 6/23
Deployment
Mid Afternoon this first installation began with towing the trailer to the site which was 45 minutes away high up a mountain to the Southeast of Grand Goave. The terrain is verdant but rugged and customer access is mostly by steep trails.
Once there, the operators’ team cleaned the site, pointed the trailer to the south, unpacked the unit and deployed the solar panels. The process took a total of 2 hours with oversight from the CSI-Sirona team
Result
Deployment went very smoothly and finished at dark. Questions were answered until the operators felt confident.
All 40 home units are committed and by the next day 17 had been picked up.